CAG Blasts Defence PSUs For Delays And Defective Items


From failing to meet the Army’s UAVs requirements to defective and life threatening parachutes and critical quality problems in the Pinaka rocket systems, the Comptroller and Auditor General has come down heavily on India’s state-run defence research and production sector.

In a report tabled this week in Parliament, the CAG states that two types of Unmanned Aerial Vehicle (UAV) could not be inducted into the Army due to severe delay in their development by the DRDO.

Among issues listed are problems with the airframe, engine and payload that have impacted the Army’s aerial surveillance capability. In a particular model’s case, all four trial unmanned planes were lost to crashes.

The auditor has said that Ordnance Parachute Factory Kanpur met production targets for parachutes only in five instances out of 49 analysed and faced complaints from the forces.  Read More

You may also read!

Malegaon Blast: NIA Court Refuses To Drop UAPA Charges Against Col. Shrikant Purohit

A National Investigation Agency (NIA) court on Saturday reportedly rejected the petition filed by Lieutenant Colonel Shrikant Purohit, one

Read More...

Iranian Security Personnel Abducted At Pakistan Border; Terrorist Group Claims Responsibility

Fourteen Iranian security personnel were reportedly kidnappped at the Southeastern border with Pakistan, reports Aljazeera. Iran's top security force,

Read More...

Kannur international airport set to get its first ATF supply

The first truck carrying aviation turbine fuel (ATF) for Kannur International Airport started off from BPCL Kochi Refinery. The

Read More...

Leave a reply:

Your email address will not be published.

Mobile Sliding Menu